Kirkwood Subdivision, Halswell

100 lot subdivision with extensive water main installation

Kirkwood subdivision involved 16500m3 cut/fill earthworks, road construction which included 9500m2 asphalt, over 2700m kerbs and channel, and all sewer and stormwater, including all necessary dewatering and trench shoring.

 

Watermain installation and service trenching were all completed in-house; construction of retaining walls, fencing and landscape basins also was completed under contract for this 100 lot development.

Client

Gillman Wheelans

Time Frame

From April 2014 to June 2015

Contract Scale

Over $4,000,000

“Whilst we are guided by our Safety and Quality Management Systems, we still believe in the integrity of a handshake.”
0800 483 926   

[email protected]    

55 Lunns Road, Middleton, Christchurch 8543, New Zealand    
© 2020 Texco. All rights reserved. | Privacy Policy

Powered by Website Angels