Riccarton Interceptor

Deep sheetpiling and trenching works

Client: Citycare Civil Ltd for Christchurch City Council
Time Frame: From March 2017 to July 2018
Contact Scale: Over $1,000,000

Under-road deep retaining structures enabled the installation of a pump station, weir structure and manholes. Texco Drilling and Piling Ltd and Texco Excavating Ltd worked together to deliver sheetpiling and dewatering, trench sheetpiling and well drilling. 

Together Texco coordinated closely with the local government client and roading contractor City Care to achieve tight timeframes set for completion. Pro-active management of water discharge volumes was required, due to the depth of excavation - the pump station box excavation went to 10m below ground level.